Completed Project Management Projects

Foundation Drain Inspection Peace Canyon Dam

Duration: March 2018 - November 2018

Project: SCL was hired by BC Hydro Generations to deliver a foundation drain inspection project at the Peace Canyon dam.  The Project will be followed by a drain cleaning project in 2019. 

 

Services: Procurement, site safety coordination, developed the master schedule, organized and led the pre-job meeting, ensured safety and environmental compliance, monitored variances in the budget, schedule and scope and created a comprehensive completion report.

2018-07-16 10.16.31.jpg
Walter Hardman Dam Safety Investigation

Duration: March 2017 - November 2018

Project: SCL was hired by BC Hydro Dam Safety to deliver a dam safety investigation project at the Walter Hardman dam.  The Project was carried out over 2 years, 2017 and 2018, in order to gather the required information for the Dam Safety Review. 

 

Services: Procurement, site safety coordination, developed the master schedule, organized and led the pre-job meeting, ensured safety and environmental compliance, monitored variances in budget, schedule and scope and created a comprehensive completion report.

20181121_162939984_iOS.jpg
Storm Water Management Plan

Duration: January 2018 - May 2018

Project: SCL was hired to prepare an Environmental Management Plan for the long-term management of seasonal storm water Run-off at an Asphalt Plant.

 

Services: Created project scope documentation, insured all associated legal documentation was reviewed and applied, created a long-time scheduled for water quality sampling, and organized lab analysis of samples..

IMG_20180406_105959.jpg
Strathcona Rock Scaling

Duration: June 2017 - November 2017

Project: During a maintenance inspection unstable rock above the Strathcona Dam was identified. SCL managed the project to remove the loose rocks and inspect the rock face.​

 

Services: Created project scope documentation, procured and monitored contractor, created master construction schedule and created a comprehensive completion report. 

P1210554.jpg
Quinsam River Diversion Canal Joint and Concrete Repairs

Duration: March 2017 - September 2018

Project: The Quinsam river diversion canal required expansion joint and spot concrete repairs along the whole diversion canal, ~1km.  

 

Services: Created project scope documentation, helped to determine the best long-term solution for the expansion join repairs, procured and monitored contractor, created master construction schedule and created a comprehensive completion report. 

2017-08-17 09.34.08.jpg
Wahleach Dam Crest Road and Lock Block Rehabilitation

Duration: March 2017 - September 2018

Project: Over time the Wahleach Dam crest road and lock blocks required rehabilitation and repairs. The goal of the project was to rehabilitate the road and lock blocks to the original design. 

 

Services: Created project scope documentation, helped determine the best long-term solution for the expansion join repairs, procured and monitored contractor, created master construction schedule and created a comprehensive completion report. 

2017-10-10 15.02.43.jpg
Peace Canyon Dam Parking Lot Repaving

Duration: March 2017 - June 2018

Project: SCL hired by BC Hydro Generation to deliver a Parking Lot Repaving project. It was identified that water pooling in the parking lot was causing a seasonal safety issue. 

 

Services: Procurement, developed the master schedule, organized and led the pre-job meeting, ensured safety and environmental compliance, monitored variances in budget, schedule and scope and created a comprehensive completion report.

IMG_3450.JPG
G.M. Shrum Generating Station Drainage Adit Access Repair

Duration: March 2017 - November 2017

Project: The overall objective of this project is to improve the rock fall protection around drainage adits, ditching and cleaning the winter sand.

 

Services: Created project scope documentation, procured and monitored consultants and contractors, created master construction schedule, provide site safety coordination and created a comprehensive completion report. 

2018-02-21 10.33.34.jpg
Strathcona Flume Concrete Repair Work

Duration: January 2017 - July 2018

Project: SCL was hired  to deliver a concrete repair work project on the Hallow-Cone Valve Concrete flume at the Strathcona Dam. The project included cast in place concrete and to lay new rebar where there were damaged or lost sections.

 

Services: Created project scope documentation, Procured and monitored contractor, Created master construction schedule and created a comprehensive completion report. 

IMG_7555.JPG
Jordan River Road Rehabilitation

Duration: January 2017 - October 2017

Project: Over time the Jordan River road becomes over grown with vegetation and difficult to drive due to erosion. The purpose of the project was to rehabilitate the Jordan River road. 

 

Services: Created project scope documentation, procured and monitored contractor, created master construction schedule and created a comprehensive completion report. 

2020-06-12 15.27.45.jpg
Overhead Crane Training and Authorization Program

Duration: February 2016 - September 2018

Project: Implement a WorkSafe compliant fixed crane operator training program. 

 

Services: Created project scope documentation, assemble a technical user group, procured and monitored training consultant, created master training rollout schedule. Led a one day training curriculum workshop and completed a rollout presentation to each generation station. 

2017-08-29 15.40.57-1.jpg
Mica Dam U1 Trash Rack Cleaning

Duration: February 2016 - May 2017

Project: Manage the trash rack cleaning project a Mica Dam. The scope included assembling a barge for the crane to situate itself near the trash rack, real-time acoustic surveying to guide the crane operator and debris disposal

 

Services:  Created project scope documentation, procured and monitored consultants and contractors, created master construction schedule, provide site safety coordination and created a comprehensive completion report. 

2017-04-26 14.51.20.jpg
Seven Mile Dam Road Realignment

Duration: May 2015 - November 2017

Project: Provide a project solution to ensure safe passage for vehicles traveling along the Seven Mile Dam Access road.  The included a geotechnical investigation, road rehabilitation design and executing the design.

 

Services: Procured and monitored consultants and construction contractor, provided on site construction management, facilitated the acquisition of all safety permits, provided safety and environmental recommendations, created master construction schedule and created a comprehensive completion report. 

2015-09-29 13.48.49.jpg
Elko Dam Public Warning System

Duration: May 2014 - March 2016

Project: BC Hydro hired SEC to plan and install a public warning system at the Elko Dam.  ​

 

Services: Scope development, held public engagement meeting, developed construction schedule, monitored design and installation work and provided a comprehensive completion report.

2015-05-05 10.06.07.jpg
Alberfeldie Dam Intakes Dredge

Duration: January 2014 - September 2015; May 2019 - June 2019

Project: BC Hydro dredges the Aberfeldie Dam headpond regularly to ensure flow into their generator intakes. In June 2014, BC Hydro undertook a larger dredge to remove sediment from the ABN headpond. Sediment removal occurred again in 2019.

 

Services: Prepared reports for DFO, obtained environmental approvals, provided on site project management, procured contractors and helped monitor budget, scope and schedule. 